Greencastle, IN
New Wastewater Treatment Plant, Lift Station & Collection System Improvements
HWC directed this project to relieve the city of Greencastle from a sewer connection ban, helping to open the new Veteran’s Memorial Highway for new economic development, and allowing the construction of a new senior citizens center and the new Putnam County Jail.
Project Highlights:
- Project cost – $12.5 million
- Over 5,000’ of 36” gravity sewer constructed
- 3 lift stations constructed
- First Vertical Loop Reactor type of treatment facility to receive a construction permit in the state of Indiana
- Received Merit Award from Indiana Chapter of ACEC
- Plant can handle peak, wet weather flows, with documented increases of flow from 1.8 MGD to 14 MGD in a 24-hour period receiving full treatment with no bypasses or overflows
- Financed using an IDEM SRF Program
- Power consumption went down 12%
- Staff labor consolidated to one shift