Muncie, IN
Airpark Shell Building
HWC Engineering is working with Hillcroft Services to complete improvements to the Airpark Shell Building, a developed site that is currently vacant.
The site currently consists of a vacant building, drive lanes, parking spaces, and truck docks.
Project improvements include:
-
- A 45,000 square foot building addition
- Moving the truck docks from the east side to the west side of the existing building
- Constructing an additional parking lot and drive lanes.
The improvements will be constructed in two phases. Phase I consists of the movement of the truck docks and the addition of a small parking lot. Phase II consists of the building addition and the addition of a larger parking lot and a drive aisle for bus drop off.